4535 611 98931 iE33 Service Manual Page 227
CSIP Level 1 Preventive Maintenance: Control Panel Articulation
Control Panel
Articulation
The recommended interval for control panel articulation maintenance is every 12 months.
➤ To check control panel articulation
1. Check the control panel articulation for smooth operation (up-down and left-right).
2. Check the control panel side-to-side release mechanism for proper operation (Figure 8-6):
a. Check control panel side-to-side movement. Adjust the tension if necessary (Figure 7-5).
b. Check the control panel swivel movement.
3. Check the control panel vertical-release lever for proper operation. Adjust the cable tension
on the release lever if necessary (Figure 7-7).
4. Check the control panel articulation-arm movement. Adjust the tension at the base of the
arm if necessary (Figure 7-8).
5. Check that the keyboard slide mechanism is fully functional. Adjust the slide catch if neces-
sary (Figure 7-6).
6. Verify that the keyboard light turns on when the keyboard is pulled out and turns off when
the keyboard is pushed in. Adjust the keyboard if necessary.