Ch 6 page 27
ELECTRICAL SYSTEM
SHOP MANUAL
Product final inspection
The following controls are performed on each unit before leaving SNDC.
1)HEATER CONTROL
Tightness test
Water valve operation (opening/closing)
2)AIR CONDITIONING CONTROL
Tightness test
Thermostat connection
3)ELECTRICAL FUNCTIONS
Control panel backlight
Control panel display
Fresh air door operation (opening/closing)
Amperage when blower is operating at full speed
Outside temperature measurement
Inside temperature measurement
Electrical continuity
Low and high pressure switches connexion