Maintenance Object Repair Procedures
555-233-123
10-1988 Issue 4 May 2002
Notes:
a. This port has been busied out with the busyout port PCSSpp command.
b. The circuit pack has been removed or has been insane for more than 11
minutes. To clear the error, replace or reinsert the circuit pack.
c. The NPE Crosstalk Test(#1103) failed.
d. The VC Summer Port Local TDM Loopback Test(#1100) failed.
System Technician-Demanded Tests: Descriptions
and Error Codes
Always investigate tests in the order presented in the table below. By clearing
error codes associated with the Voice and Control Channel Local Loop Around
Test, for example, you may also clear errors generated from other tests in the
testing sequence.
NPE Crosstalk Test (#6)
This test is destructive.
The NPE Crosstalk test verifies that this ports NPE channel talks on the selected
time slot and never crosses over to time slots reserved for other connections. If
the NPE is not working correctly, one-way and noisy connections may be
observed. This test is part of the ports long test sequence and takes
approximately 20 to 30 seconds to complete.
Order of Investigation
Short Test
Sequence
Long Test
Sequence D/ND
1
1 D = Destructive; ND = Nondestructive
NPE Crosstalk Test (#6) (a) X D
TDM Loopback Test (#1100) X X D

Table of Contents