10.2 Requirements for commissioning
Description
• You have correctly installed the converter and the motor.
• You have mounted the motor, including an encoder that might be required, onto the
mechanical system.
• You have connected the motor to the converter.
• You have connected the converter and the operating unit via service interface X127 or
PROFINET interface X150.
• You have switched on the converter supply voltage.
• The converter has ramped up.
Commissioning (web server)
10.2Requirements for commissioning
SINAMICS G220 converter
210 Operating Instructions, 04/2024, FW V6.2, A5E51781573B AB