15.1.4 LED RDY and LED COM
Response of the LEDs
RDY COM Description Remedy
Green
Not rele‐
vant
Converter is ready for operation and is fault free.
Not rele‐
vant
Green
Cyclic communications running.
Green Green
Possible causes
• Firmware is being updated.
• All user-dened settings are reset to the factory
setting.
Green
Firmware update completed
The converter is waiting.
Switch the converter supply voltage o and on.
Green
All user-dened settings are reset to the factory
setting.
Switch the converter supply voltage o and on.
Green
Not rele‐
vant
PROFIenergy energy saving mode is active.
Orange
Green
Commission or restore factory settings using the
commissioning tool
Orange
Temporary state after the supply voltage is switch‐
ed on: rmware being loaded and initialized.
Orange Orange
Possible causes
• Temporary state after the supply voltage is
switched on
• Restart
Orange
Converter detection via DCP ashing.
System messages
15.1LEDs
SINAMICS G220 converter
Operating Instructions, 04/2024, FW V6.2, A5E51781573B AB 737