Procedure
1. Click on icon
(Upload from device) in the toolbar.
The "Upload preview" dialog opens. Startdrive checks whether all requirements for loading
have been met. In the event of any obstructions, these are displayed as messages in the
dialog.
2. Check the messages. If necessary, activate the actions in column "Action".
As soon as uploading becomes possible, the "Upload from device" button is enabled.
3. Click the "Upload from device" button.
The data, except for the UMAC con󹪝guration, is loaded from the converter into the project.
The drive data is saved with the project.
11.2.4 Loading project data into the drive
Overview
Load the data from your Startdrive project into a drive.
Requirement
A project has been created.
A drive has been created and completely con󹪝gured in the project.
Optional: There isanactive online connection between the drive and operating unit.
For activated user management (UMAC) in Startdrive:
The following function rights are activated for your user account:
"Download to drives"
"Manage users and roles" (the UMAC con󹪝guration must be loaded to the drive)
For activated user management (UMAC) in the converter:
Depending on which data is loaded to the converter, you require the corresponding function
rights for your user account.
Details on this topic are provided in the Con󹪝guration Manual SINAMICS Industrial Security
(
https://support.industry.siemens.com/cs/ww/en/view/109810578) in section "Security
settings in Startdrive".
Commissioning (Startdrive)
11.2Basics
SINAMICS G220 converter
278 Operating Instructions, 04/2024, FW V6.2, A5E51781573B AB

Table of Contents

Related product manuals