Maintenance Object Repair Procedures
555-233-123
10-318 Issue 4 May 2002
BRI Set Audits Test (#630)
This is a series of two tests which are classified as audits. The switch sends
messages to the BRI endpoint to perform the following tests:
■ Ringer Audit - This audit ensures that both the switch and the endpoint
agree as to the current state of the endpoint’s ringer.
■ Lamps Audit - This audit ensures that both the switch and the endpoint
agree as to the current state of the endpoint’s lamps.
■ Call Activity Audit - This audit ensures that the state of calls is consistent
between the switch and the endpoint.
This test is not executed for ASAI or Avaya adjunct because adjuncts do not
employ ringers or lamps, or establish calls on the B-channels associated with the
BRI interface.
2069 ABORT The endpoint has returned an error response to the switch
sent application message.
1. Retry the command at 1-minute intervals a maximum of 5
times.
2000 FAIL No response is received from the endpoint or the adjunct. For
BRI endpoints:
1. Consult the endpoint documentation to determine if
ISDN-BRI Management and Maintenance Procedures are
supported. If not supported, use the change station
extension command to change the “MIMs Supported?”
field to “no.” Use the busyout station extension and
release station extension commands to busyout and
release the endpoint to resolve any endpoint alarms
resulting from failure of this test.
2. If the endpoint supports these procedures and the test
continues to fail, assume the endpoint is defective and
replace it.
PASS The endpoint has successfully responded to the switch’s
application message.
Table 10-125. TEST #629 BRI Layer 3 Query — Continued
Error
Code
Te s t
Result Description/Recommendation
Continued on next page