Table 10-501. TEST #1275 SCOTCH Synchronous Looparound Test
Error
Code
Te s t
Result Description/Recommendation
1000 ABORT The port is in use or PPP link is connected.
1. Determine when the port is available for testing (status
clan-port UUCSSpp).
2. The port may be forced to the idle state by executing a
busyout port UUCSSpp command.
NOTE:
This command is destructive, causing all calls and links
using the port to be torn down.
1002 ABORT No TDM bus timeslots available for the test.
1. Retry the command at 1-minute intervals, up to 5 times.
2. Escalate if the problem persists.
1963 ABORT Firmware indicates that the port is in use or ppp link is connected.
1. Determine when the port is available for testing (status
clan-port UUCSSpp).
2. The port may be forced to the idle state by executing a
busyout port UUCSSpp command.
NOTE:
This command is destructive, causing all calls and links
using the port to be torn down.
2000 ABORT Did not receive circuit pack test response within the allowable
time period.
1. If this problem persists, reset the circuit pack (busyout
board UUCSS, reset board UUCSS, and release board
UUCSS).
2. If the problem persists, replace the circuit pack.
2012 ABORT Internal system error.
1. Retry the command at 1-minute intervals, up to 3 times.
2. Escalate if the problem persists.