Maintenance Object Repair Procedures
555-233-123
10-1578 Issue 4 May 2002
Switch Control Reset Test (#93)
This test is destructive.
This test resets the Switch Control and determines if it can successfully go
through its initialization sequence. The test is destructive since there is the
possibility of losing some control messages to or from port circuit packs.
Table 10-583. TEST #93 Switch Control Reset Test
Error
Code
Te s t
Result Description/Recommendation
2012 ABORT Internal system error
2013
2100
none
ABORT Could not allocate the necessary system resources to run this
test.
1. Retry the command at 1-minute intervals a maximum of 5
times.
1029
2014
2015
2016
2017
2018
2020
2022
2024
2025
2051
ABORT Refer to STBY-SPE for a description of these error codes
2000 or
None
FAIL The Switch Control could not be successfully reset. If this is a
standard system, the customer probably cannot make or
receive calls.
1. This failure could be due to either a NetPkt or Netcon
circuit pack failure or the loss of system timing signals. If
the Switch Control is alarmed, then suspect a NetPkt or
Netcon circuit pack failure. If the Switch Control is not
alarmed, investigate the possible loss of system timing
signals. See TDM Bus Clock. If many port circuit pack
LEDs are lit, suspect a TDM Bus Clock problem. If only
the NetPkt or Netcon circuit pack LED is lit, suspect the
NetPkt or Netcon circuit pack. If the NetPkt or Netcon
circuit pack is determined to be at fault, proceed to Step
2.
2. If calls cannot be made, replace the NetPkt or Netcon
board.
PASS The Switch Control has initialized correctly. Look at results of
the other tests to see if it is operating correctly.
Continued on next page