Requirement
Note
Commissioning cannot be started
If other users are accessing the converter via the web server and controlling the converter via the
control panel or have started a commissioning operation, commissioning will not be possible.
A corresponding message appears.
Description of function
The most important parameters of the converter are set during commissioning. Once
commissioning has been completed, the converter knows, for example, the data of the
connected motor and has adapted its control interfaces to the requirements.
Starting/canceling the advanced setup
The following options are available, depending on whether the converter has already been
con󹪝gured:
Keep current settings and start commissioning
Reset converter to factory settings and start commissioning
The converter creates a restore point when commissioning is started. The converter saves the
changes after every commissioning step. If you cancel commissioning, then the converter is
reset to the restore point.
Starting commissioning in read-only mode
To get to know the drive options and functions 󹪝rst, the commissioning can be started and
run through in read-only mode.
Commissioning (web server)
10.5Functions and menus
SINAMICS G220 converter
230 Operating Instructions, 04/2024, FW V6.2, A5E51781573B AB