(6) Wind two layers of insulation tape on the layers of film strip.
(a) Start the first layer of tape one inch to 1.5 inches from the end of the splice.
(b) Wind the tape on the splice 1 to 1.5 inches farther than the other end of the splice.
Make sure that each edge of the tape makes a 50 percent overlap with the tape below it.
(c) Start the second layer a tape where the first layer of tape ends.
(d) Wind the tape on the first layer of tape in the direction of the start of the first layer of tape.
Make sure that:
• Each edge of the tape makes a 50 percent overlap with the tape below it
• The second layer of tape is wound in the opposite direction of the first layer of tape
• The second layer of tape ends where the first layer of tape starts.
(7) Assemble three lacing tape wire harness ties on the layers of tape.
Refer to Subject 20-10-11 for the procedure to assemble a wire harness tie.
Make sure that:
• The lacing tape is Temperature Grade D material
• A wire harness tie is assembled at each end of the layers of tape
• A wire harness tie is assembled at the center of the layers of tape.
B. Splice Removal
(1) Remove the insulation sleeves or layers of insulation tape from the splice.
(2) Remove one end of the splice from the wire. Refer to Figure 28.
ASSEMBLY AND REPAIR OF THE AMP AND BACS52N COPALUM SPLICES
707, 727-787
STANDARD WIRING PRACTICES MANUAL
20-30-13
Page 38
Oct 15/2015D6-54446
ECCN 9E991 BOEING PROPRIETARY - See title page for details