4.1.2 Installation procedures
Table 4-1 Hicom 150 E OfficePro - procedures for system installation
Step Installation activity (notes)
1. Select the installation site
(generally already predefined)
page 4-3
2. Unpack the components page 4-3
3. Mount the main distribution frame MDFU/MDFU-E page 4-4
4. Set up the system cabinets:
Remove the cabinet cover
Single cabinet
Two cabinets (stacked)
Two cabinets (side-by-side)
Three cabinets (stacked)
Mount the base elements
(for stacked system cabinets)
Starting on
page 4-5
5. Earth the system
Check the protective earth
Starting on
page 4-12
6. Connect the cable page 4-16
7. Lay out the line network and set the jumpers on the MDFU/MDFU-E page 4-23
8. Load the system software (flash memory card) page 4-27
9. Configuration instructions
(board configuration, already completed)
page 4-28
10. Connect terminals page 4-34
11. Perform visual inspection page 4-34