(b) Install A/C compressor belt. Refer to COOL-
ING SYSTEM for procedure.
(5) Position wire harness on cylinder head cover
and install retaining nuts (Fig. 58).
(6) Install ignition coils and connect all electrical
connectors.
(7) Install upper intake manifold and air cleaner
assembly.
SPARK PLUG TUBES
REMOVAL
(1) Remove cylinder head cover(s). Refer to proce-
dure in this section.
(2) Using locking pliers remove the tube from the
cylinder head (Fig. 63). Discard old tube.
(3) Clean area around spark plug with Mopart
Parts Cleaner or equivalent.
(4) Refer to Cylinder Head Covers for spark plug
tube seal replacement.
INSTALLATION
(1) Apply Mopart Stud and Bearing Mount to a
new tube approximately 1 mm (0.039 in.) from the
end of tube, ina3mm(0.118 in.) wide area.
(2) Install sealer end of tube into the cylinder
head. Then carefully install the tube using a hard-
wood block and mallet. Install the tube until it is
seated into the bottom of the bore.
(3) Install cylinder head cover(s). Refer to proce-
dure in this section.
CYLINDER HEAD
REMOVAL
(1) Drain cooling system. Refer to COOLING SYS-
TEM for procedure.
Fig. 59 Ignition Coils
Fig. 60 Cylinder Head Covers
1 – CYLINDER HEAD COVER-LEFT SIDE
2 – BOLTS (8)
Fig. 61 Cylinder Head Cover Gasket and Spark Plug
Tube Seals
1 – CYLINDER HEAD COVER GASKET
2 – SPARK PLUG TUBE SEALS
Fig. 62 Spark Plug Tube Seal Installation
1 – SPECIAL TOOL MD-998306
2 – SPARK PLUG TUBE SEAL
9 - 112 3.2/3.5L ENGINE LH
REMOVAL AND INSTALLATION (Continued)