Chapter 5 Turn Up a Network
NTP- D258 Provision an Open-Ended SNCP
NTP-D258 Provision an Open-Ended SNCP
Step 1 Verify that the fiber is correctly connected to the SNCP trunk (span) STM-N cards at each open-ended
SNCP node. Figure 5-11 shows an example. Node 1 is connected to ONS 15454 SDH Nodes 2 and 3
through Slots 12 and 5. Trunk cards at Nodes 2 and 3 are connected to the third-party vendor equipment.
Purpose This procedure provisions ONS 15454 SDH nodes in an open-ended SNCP
connected to a third-party vendor network. This topology allows you to
route a circuit from one ONS 15454 SDH network to another
ONS 15454 SDH network through a third-party network.
Tools/Equipment None
Prerequisite Procedures NTP-D35 Verify Node Turn-Up, page 5-2
Required/As Needed As needed
Onsite/Remote Onsite
Security Level Provisioning or higher