1-4
Cisco ONS 15454 SDH Procedure Guide, R7.0
78-17194-01
Chapter 1 Install the Shelf and FMECs
NTP- D1 Unpack and Inspect the ONS 15454 SDH Shelf Assembly
Note Ring runs are not provided by Cisco and can hinder side-by-side shelf installation where space is limited.
Tools Needed
To install the ONS 15454 SDH, you need the following tools:
• #2 Phillips screwdriver
• Medium slot-head screwdriver
• Small slot-head screwdriver
• Video fiber connector inspection instrument
• CLETOP cleaning cassette
• Crimping tool—This tool must be large enough to accommodate the girth of the grounding lug when
you crimp the grounding cable into the lug.
• Wire stripping tool
Test Equipment
To install the ONS 15454 SDH, you need the following test equipment:
• Voltmeter
• Power meter (only for use with fiber optics)
• Bit error rate (BER) tester for E1-N-14, E1-42, E3-12, DS3i-N-12, STM1E-12, and FMEC cards
NTP-D1 Unpack and Inspect the ONS 15454 SDH Shelf Assembly
Step 1 Complete the “DLP-D1 Unpack and Verify the Shelf Assembly” task on page 17-1.
Step 2 Complete the “DLP-D2 Inspect the Shelf Assembly” task on page 17-2.
Step 3 Continue with the “NTP-D2 Install the Shelf Assembly” procedure on page 1-5.
Stop. You have completed this procedure.
Purpose This procedure unpacks the ONS 15454 SDH and verifies the contents.
Tools/Equipment Pinned hex (Allen) key for front door
Prerequisite Procedures None
Required/As Needed Required
Onsite/Remote Onsite
Security Level None