5-3
Cisco ONS 15454 SDH Procedure Guide, R7.0
78-17194-01
Chapter 5 Turn Up a Network
NTP- D124 Provision a Point-to-Point Network
Step 4 Click the Provisioning > General tabs. Verify that all general node information settings match the
settings of your site plan. If not, see the “NTP-D81 Change Node Management Information” procedure
on page 11-2.
Step 5 Click the Provisioning > Timing tabs. Verify that timing settings match the settings of your site plan.
If not, see the “NTP-D85 Change Node Timing” procedure on page 11-6.
Step 6 Click the Provisioning > Network tabs. Ensure that the IP settings and other CTC network access
information is correct. If not, see the “NTP-D201 Change CTC Network Access” procedure on
page 11-2.
Step 7 Click the Provisioning > Protection tabs. Verify that all protection groups have been created according
to your site plan. If not, see the “NTP-D203 Modify or Delete Card Protection Settings” procedure on
page 11-5.
Step 8 Click the Provisioning > Security tabs. Verify that all users have been created and their security levels
and policies match the settings indicated by your site plan. If not, see the “NTP-D205 Modify Users and
Change Security” procedure on page 11-7.
Step 9 If SNMP is provisioned on the node, click the Provisioning > SNMP tabs. Verify that all SNMP settings
match the settings of your site plan. If not, see the “NTP-D87 Change SNMP Settings” procedure on
page 11-7.
Step 10 Provision the network using the applicable procedure shown in the “Before You Begin” section on
page 5-1.
Stop. You have completed this procedure.
NTP-D124 Provision a Point-to-Point Network
Step 1 Complete the “DLP-D60 Log into CTC” task on page 17-49 on an ONS 15454 SDH in the network
where you want to provision a point-to-point configuration.
Step 2 Click the Provisioning > Protection tabs. Verify that 1+1 protection is created for the STM-N cards.
Complete the “DLP-D73 Create a 1+1 Protection Group” task on page 17-64 if protection has not been
created.
Step 3 Repeat Steps 1 and 2 for the second point-to-point node.
Step 4 Verify that the working and protect cards in the 1+1 protection groups correspond to the physical fiber
connections between the nodes, that is, verify that the working card in one node connects to the working
card in the other node, and that the protect card in one node connects to the protect card in the other node.
Purpose This procedure provisions two ONS 15454 SDHs in a 1+1 point-to-point
(terminal) network.
Tools/Equipment None
Prerequisite Procedures NTP-D35 Verify Node Turn-Up, page 5-2
Required/As Needed As needed
Onsite/Remote Onsite
Security Level Provisioning or higher