NTP- D307 Provision an Integrated MS-SPRing/SNCP Dual-Ring Interconnect
NTP-D307 Provision an Integrated MS-SPRing/SNCP Dual-Ring
Interconnect
Step 1 Complete the “DLP-D60 Log into CTC” task on page 17-49 at a node in the MS-SPRing and SNCP DRI
network. If you are already logged in, continue with Step 2.
Step 2 Complete the following steps if you have not provisioned the MS-SPRing and SNCP that you will
interconnect in an integrated DRI. If the MS-SPRing and SNCP are created, continue with Step 3.
a. To provision and test the MS-SPRing, complete the following:
NTP-D40 Provision MS-SPRing Nodes, page 5-10
NTP-D41 Create the MS-SPRing, page 5-13
NTP-D341 Two-Fiber MS-SPRing Acceptance Test, page 5-14
NTP-D342 Four-Fiber MS-SPRing Acceptance Test, page 5-16
b. To provision and test the SNCP, complete the following:
NTP-D44 Provision SNCP Nodes, page 5-22
NTP-D343 SNCP Acceptance Test, page 5-24
Step 3 Verify that the MS-SPRing and SNCP DRI interconnect nodes have STM-N cards installed and have
fiber connections to the other interconnect node:
The STM-N cards that will connect the MS-SPRing and SNCP must be installed at the interconnect
nodes. The STM-N cards in the SNCP nodes and the interconnect nodes must be the same type.
The interconnect nodes must have the correct fiber connections. An example is shown in
Figure 5-10.
Purpose This procedure provisions an MS-SPRing and an SNCP in an integrated
DRI topology.
Tools/Equipment None
Prerequisite Procedures NTP-D35 Verify Node Turn-Up, page 5-2
Required/As Needed As needed
Onsite/Remote Onsite
Security Level Provisioning or higher