21-46
Cisco ONS 15454 SDH Procedure Guide, R7.0
78-17194-01
Chapter 21 DLPs D400 to D499
DLP- D469 Create a Two-Fiber MS-SPRing Manually
Note The numbers in parentheses after the node name are the MS-SPRing node IDs assigned by
CTC. Every ONS 15454 SDH in an MS-SPRing is given a unique node ID, 0 through 31. To
change it, complete the “DLP-D24 Change an MS-SPRing Node ID” task on page 17-19.
Step 9 Return to your originating procedure (NTP).
DLP-D469 Create a Two-Fiber MS-SPRing Manually
Step 1 In node view, click the Provisioning > Ring tabs.
Step 2 Click Create.
Step 3 In the Suggestion dialog box, click OK.
Step 4 In the Create MS-SPRing dialog box, set the MS-SPRing properties:
Ring Type—Choose two-fiber.
Ring Name—Assign a ring name. You must use the same ring name for each node in the
MS-SPRing. Any alphanumeric character string is permissible, and uppercase and lowercase letters
can be combined. Do not use the character string “All” in either upper or lower case letters; this is
a TL1 keyword and will be rejected. Do not choose a name that is already assigned to another
MS-SPRing.
Node ID—Choose a Node ID from the drop-down list (0 through 31). The Node ID identifies the
node to the MS-SPRing. Nodes in the same MS-SPRing must have unique Node IDs.
Reversion time—Set the amount of time that will pass before the traffic reverts to the original
working path. The default is 5 minutes. All nodes in an MS-SPRing must have the same reversion
time setting.
West Line—Assign the west MS-SPRing port for the node from the drop-down list.
The east and west ports must match the fiber connections and DCC terminations set up in the “NTP-D40
Provision MS-SPRing Nodes” procedure on page 5-10.
East Line—Assign the east MS-SPRing port for the node from the drop-down list.
Step 5 Click OK.
Note Some or all of the following alarms will appear until all the MS-SPRing nodes are provisioned:
E-W MISMATCH, RING MISMATCH, APSCIMP, APSDFLTK, and MS-SPRINGOSYNC. The
alarms clear after you configure all of the nodes in the MS-SPRing.
Purpose This task creates a two-fiber MS-SPRing at each MS-SPRing-provisioned
node without using the MS-SPRing wizard.
Tools/Equipment None
Prerequisite Procedures DLP-D60 Log into CTC, page 17-49
Required/As Needed Required
Onsite/Remote Onsite or remote
Security Level Provisioning or higher