DLP-D1 Unpack and Verify the Shelf Assembly
Step 1 When you receive the ONS 15454 SDH system equipment at the installation site, open the top of the box.
The Cisco Systems logo designates the top of the box.
Step 2 Remove the foam inserts from the box. The box contains the ONS 15454 SDH shelf (wrapped in plastic)
and a smaller box of items needed for installation.
Step 3 To remove the shelf, grasp both rings of the shelf removal strap and slowly lift the shelf out of the box.
Step 4 Open the smaller box of installation materials, and verify that you have all items listed in the
“Cisco-Supplied Equipment” section on page 1-2.
Note The fan-tray assembly is shipped separately.
Step 5 Return to your originating procedure (NTP).
Purpose This task removes the shelf assembly from the package.
Tools/Equipment None
Prerequisite Procedures None
Required/As Needed Required
Onsite/Remote Onsite