TASK 53-05-03-210-831
38. INTERNAL - GENERAL VISUAL: FLIGHT COMPARTMENT FLOOR STRUCTURE
(Figure 243)
NOTE: This procedure is a scheduled maintenance task.
A. Location Zones
Zone Area
211 Flight Compartment - Left
212 Flight Compartment - Right
B. Access Panels
Number Name/Location
S2102 Flight Compartment Floor Structure
C. Inspection
SUBTASK 53-05-03-010-028
(1) Special Access:
Number Name/Location
S2102 Flight Compartment Floor Structure
NOTE: Remove sidewalls and floor panels as required. Remove/displace insulation blankets
as required.
SUBTASK 53-05-03-210-031
(2) Do a General Visual inspection of the flight compartment floor structure.
SUBTASK 53-05-03-910-041
(3) 737-6789 Basic Task Description, AMM Task 51-05-01-210-808.
END OF TASK