SV9100 System Hardware Manual 3-67
6. Align the upper and lower bracket holes with the heads of
anchor bolts mounted on the wall and slide downward.
7. Connect grounding wire to chassis. Refer to Chapter 4
paragraph 3.5 Installing the 9.5” Base (CHS2UG B-US) and
Expansion (CHS2UG E) Chassis on page 3-24 for complete
details on grounding the system.
8. Refer to 3.5.5 Install AC Power Cord on 9.5” Base and
Expansion Chassis on page 3-37 for installation of the
power cord or, Chapter 6 paragraph 2.1 Installation and
Safety Precautions on page 4-4 for installation of blades.
Figure 3-82 Wall Mount – Lower Side (Small Batt Box)