8.2.1 Floor Mounting the CHSG LARGE BATT BOX
1. Use the template shown in Figure 3-117 Floor Mount Spacing Guide
for required spacing before drilling holes for 0.39” (10mm) anchor
bolts (locally procured).
2. Mark and drill the four holes required to install the CHS BASE UNIT.
WARNING
Because of injury from falling equipment, wall mounting
the CHSG LARGE BATT BOX is not recommended.
Mounting the CHSG LARGE BATT BOX directly on the
floor is not recommended.
TIP
The CHS BASE UNIT raises the height of the CHSG
LARGE BATT BOX 120mm (4.72”).
When the CHSG LARGE BATT BOX and CHS2UG-US
are connected for long term use, the CHS2UG JOINT
BRACKET KIT is used.