Issue 3.0
9-8 Installing SV9100 Optional Equipment
9. Install a modular jack for each PGD(2)-U10 ADP. For each module, run
one-pair 24 AWG station cable from the cross-connect block to a modular
jack. Ground the unused pair.
10. Terminate the extension leads to GRN/RED of the modular jack. Terminate
the unused leads to the jack.
11. Install bridging clips as required.
12. Plug a modular line cord from the mod jack to the CN1 connector on the
PGD(2)-U10 ADP.
Figure 9-7 PGD(2)-U10 ADP Connections
For the module to ID correctly, set the circuit type to 0 for the port
in Program 10-03-01 prior to connecting the line cord.
❍ In some cases, while testing the operation of an extension port
that is connected to a Cordless II, Cordless Lite II, or
PGD(2)-U10 ADP, a technician may connect a line cord
directly from an extension port on the CD-8DLCA/
CD-16DLCA blade. Though this is not the recommended
connection, it can be used to test these devices.
❍ Should a direct connection of this type be made to the base
station of the Cordless II or Cordless Lite II, or to a
PGD(2)-U10 ADP, the line cord must be 2-wire (1-pair). If a
2-pair wire is used, the system provides power to the unused
pair. This can prevent the cordless telephone from acquiring a
link with the base station or it can damage the PGD(2)-U10
ADP or the SV9100 station card.
❍ The recommended connection is to punch down 2 wires to the
cross-connect block, then connect the extension block to the
RJ-61 connector on the blade.