Issue 3.0
3-94 Installing the SV9100 Chassis
3. Align bolt holes in CHS BASE UNIT (see Figure 3-117 Floor Mount
Spacing Guide on page 3-93) with holes drilled in floor and secure
using four anchor bolts.
4. Align and install the CHSG LARGE BATT BOX on top of the CHS
BASE UNIT.
5. Secure the CHSG LARGE BATT BOX to the CHS BASE UNIT using
the CHS2UG JOINT BRACKET KIT. Refer to Figure 3-118 Installing
the CHSG LARGE BATT BOX using the CHS2UG JOINT BRACKET
KIT.
8.2.2 Battery Installation
1. Loosen screw on front of CHSG LARGE BATT BOX.
2. Swing cover outward and detach from CHSG LARGE BATT BOX.
Figure 3-118 Installing the CHSG LARGE BATT BOX using the CHS2UG JOINT BRACKET
KIT
Figure 3-119 Removing CHSG LARGE BATT BOX Cover