Conversion Tasks
Issue 2.1 June 2006 1053
Conversion tasks checklist
The following checklist identifies the major tasks in the conversion procedure:
● Changing direct-connect synchronization
● Adding new circuit packs
● Upgrading firmware on new circuit packs.
● Disabling PNC duplication.
● Removing fiber administration.
● Enabling PNC duplication.
● Removing fiber-related hardware.
● Administering PN synchronization.
● Completing post-conversion tasks
Changing direct-connect synchronization, if necessary
If you are not converting the PN that contains the direct-connect synchronization source, do not
perform this procedure. Continue to Adding new circuit packs
on page 1055.
Note:
Note: The administration of synchronization for a direct-connect configuration is the
same as for a CSS synchronization. For a direct-connect configuration, the
synchronization commands and screens use “CSS.”
!
Important:
Important: Synchronization for a direct connect configuration is derived from a fiber-PNC
PN. If you are converting only one PN to IP-connect, Avaya recommends that
you do not convert the PN that contains the synchronization source. If you are
converting the PN that contains the synchronization source, convert this PN last.