Migration paths
Issue 2.1 June 2006 327
Additional tasks
Before you go on site for a migration from a DEFINITY system, complete the following
additional tasks before you start the migration:
Premigration setup
The premigration team must complete the following tasks. If these tasks are not completed, do
not continue with the migration.
For more information, see Migration paths
on page 321.
Avaya technical support
representatives only: Obtain
the static craft password.
Call the ASG Conversant number, 800-248-1234 or
1-720-444-5557 and follow the prompts to get the
password. You need the Product ID, the FL, or IL
number of the customer.
Run the Automatic
Registration Tool (ART) for
the INADS IP address, if
necessary.
This step is necessary if the configuration of the
customer INADS alarming modem has changed as
well as any changes to the system alarming
configuration.
ART is available only to Avaya associates. Business
Partners can call 800-295-0099.
Verify that you have copied
all necessary files to your
computer
These files can include:
● service packs
● license file
● authentication file
● firmware for programmable circuit packs
9
Task Description
3 of 3
9
Task Description
Verify that you have the
required, customer-provided
network information. Obtain
a completed Electronic
Preinstallation Worksheet
(EPW)
The EPW is an Excel spreadsheet that provides the
information about the network. You need this
information to configure the control network
components with the Avaya Installation Wizard. Get
the EPW from the Avaya project manager, Avaya
software technician, or customer network
administrator. A blank EPW is available at the Avaya
Installation Wizard web site (http://support.avaya.com/
avayaiw/).