Migrating translations
Issue 2.1 June 2006 341
Installing TN771 Maintenance/Test
You can install a TN771 Maintenance/Test circuit pack in any slot other than slots A01 and A02.
Avaya recommends one TN771 Maintenance/Test circuit pack per location for the following
conditions:
There are three or more G650, G600, or CMC1 cabinets in the S8400 system. Do not
include G150 and H.248 gateways in this count, and
There are IP endpoints or ISDN endpoints. These endpoints consist of:
- BRI trunks
- PRI trunks
- BRI stations
The TN8412AP S8400 IP Interface (SIPI) circuit pack provides all maintenance functions that
were present on the TN798 or TN2402 Processor circuit pack. This carrier does not have a
TN775 Maintenance (EPN) dedicated slot.
Migrating translations
This section describes how to migrate the translation files from the current system to the S8400
Media Server.
Installing the software load
To install the software load:
1. From the Services laptop, click Start > Run to open the Run window.
2. Type ping -t 192.11.13.6. Press Enter to indicate when the Services port is
responding.
3. Click Start > Run to open the Run window.
4. Type telnet 192.11.13.6. Press Enter to telnet in to the Services port on the front of
the S8400 Media Server.