Migration paths
Issue 2.1 June 2006 841
Presite migration checklist
Before you go on site, complete the following tasks:
On site migration checklist
When you are on site, complete the following tasks before you start the migration:
9
Task Description
Verify that the voice network,
dial plan, and E911 for remote
locations were redesigned.
Perform this task only if applicable.
Verify that all existing circuit
packs work with the new
system.
Check the Minimum Vintage Table. Go to the
Hardware and Software Compatibility Matrix at ftp//
ftp.avaya.com/incoming/Up1cku9/tsoweb/media/
minhardwarevintages.pdf.
Replace any TN799B/C C-LAN
circuit packs.
Replace with the TN799DP circuit pack.
Replace the 259A adapter and
the CAT3 cable.
Replace with the cable extender adapter with
Comcode 848525887 and the CAT5 or better cable.
Replace TN570 EI circuit packs. Replace with TN570B vintage 7 or later circuit packs.
9
Task Description
Verify that the EIA 310D
19-inch (48-cm) open
equipment rack is grounded.
See the job aid titled Approved Grounds
(555-245-772).
For S8710 only:
Verify that the open,
customer-supplied, EIA
310D (or equivalent)
standard 4-post, 19-inch
(48-centimeter), equipment
rack is installed correctly
and solidly secured.
Ensure that you have the screws that come with the
rack. Ensure that the rail kit for the Avaya-supplied
UPS is installed on the rack or available for
installation. For more information on installing the rail,
see the rail kit documentation.
1 of 2