Maintenance Instruction manual GLM-I
384 38.019.129.001 en
28
Activity Interval Cleaning agent/
lubricant
Rotary arm labeler Labeling chute: Spray soiling
with sufficient label remover
.
Leave it to soak in well and re-
move the label residues by
hand or with a cloth.
1.5 days Label remover,
95943000000
Clean and lubricate roller
track.
1.5 days Label remover,
95943000000
Oil, 96001740000
Rotary arm labeler Replace rotary arm labeler. 6 weeks
Piston labeler Clean suction plate, gripper. Daily Label remover,
95943000000
Turn suction piston. 6 weeks
Belt labeler Replace pressure roller. 10 weeks
Clean deflecting plate, suction
plate, gripper.
1.5 days Label remover,
95943000000
Belt labeler Clean jet. If dirty Label remover,
95943000000
Belt modules
Activity Interval Cleaning agent/lu-
bricant
Clean, replace belt. After soiling/wear
and tear
Water with standard
cleaning agents
Papst-Zeitlauf, Maxon: Replace motors. 5 years
Dunker: Replace motors. 250 days
WEG: Replace motors. 2 years
Check conveyor rollers and replace, if nec-
essary.
With each belt re-
placement
Clean belt bodies: With each belt re-
placement
Brush and label re-
mover, 95943000000

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Bizerba GLM-I and is the answer not in the manual?

Bizerba GLM-I Specifications

General IconGeneral
BrandBizerba
ModelGLM-I
CategoryLabel Maker
LanguageEnglish

Related product manuals