Cisco ONS 15454 DWDM Installation and Operations Guide, R6.0
August 2005
Chapter 1 Install the Shelf and Common Control Cards
DLP-G29 Install the Fiber-Storage Tray
Step 3 Align the chassis with the rack mounting screw holes, then insert and tighten the four screws.
Step 4 Return to your originating procedure (NTP).
DLP-G29 Install the Fiber-Storage Tray
Step 1 The fiber-storage tray requires 1 RU in a standard 19-inch (482.6-mm) or 23-inch (584.2-mm) rack.
Locate the RMU space specified in your site plan. See the “15.5 Typical DWDM Rack Layouts” section
on page 15-17 for common site configurations.
Step 2 Verify that the mounting brackets attached to the unit are correct for your rack size. Complete “DLP-G3
Reverse the Mounting Bracket to Fit a 19-inch (482.6-mm) Rack (ANSI Only)” task on page 1-10 as
required.
Step 3 Align the chassis with the rack mounting screw holes, insert the screws (4), and tighten.
Step 4 Return to your originating procedure (NTP).
DLP-G30 Install the FlexLayer Shelf
Step 1 The FlexLayer shelf requires 1 RU in a standard 19-inch (482.6-mm) or 23-inch (584.2-mm) rack.
Locate the RMU space specified in your site plan. Refer to Chapter 15, “Shelf Hardware Reference” for
typical DWDM site layout plans.
Step 2 A set of mounting brackets are included with the FlexLayer mounting kit, one set each for 19-inch
(482.6-mm) or 23-inch (584.2-mm) racks. Verify that your chassis is equipped with the correct set of
brackets for your rack. Change the brackets as required.
Purpose This task installs the fiber-storage tray. The fiber-storage tray stores slack
fiber-optic cable.
Tools/Equipment #2 Phillips screwdriver
Prerequisite Procedures None
Required/As Needed As needed
Onsite/Remote Onsite
Security Level None
Purpose This task installs the FlexLayer shelf. Perform this task if you are
installing any FlexLayer modules.
Tools/Equipment #2 Phillips screwdriver
FlexLayer shelf assembly (15216-FL-SA)
Prerequisite Procedures None
Required/As Needed As needed
Onsite/Remote Onsite
Security Level None