Chapter 3 Turn Up a Node
NTP-G25 Set Power Monitor Thresholds
NTP-G25 Set Power Monitor Thresholds
Caution The default battery power thresholds are normally not changed. Threshold changes should only be
performed at the direction of your site administrator.
Step 1 Complete the “DLP-G46 Log into CTC” task on page 2-25 for the node you will set up. If you are already
logged in, continue with Step 2.
Step 2 In node view, click the Provisioning > General > Power Monitor tabs.
Step 3 To change the extreme low battery voltage threshold in 0.5 VDC increments, choose a voltage from the
ELWBATVGVdc drop-down list.
Step 4 To change the low battery voltage threshold in 0.5 VDC increments, choose a voltage from the
LWBATVGVdc drop-down list.
Step 5 To change the high battery voltage threshold in 0.5 VDC increments, choose a voltage from the
HIBATVGVdc drop-down list.
Step 6 To change the extreme high battery voltage threshold in 0.5 VDC increments, choose a voltage from the
EHIBATVGVdc drop-down list.
Step 7 Click Apply.
Stop. You have completed this procedure.
Purpose This procedure provisions extreme high, extreme low, and low input
battery power thresholds within a –48 VDC environment. When the
thresholds are crossed, the TCC2/TCC2P generates warning alarms in
CTC. For ONS 15454 power specifications, see Appendix B, “Hardware
Specifications.”
Tools/Equipment None
Prerequisite Procedures NTP-G22 Verify Common Card Installation, page 3-4
Required/As Needed Required
Onsite/Remote Onsite or remote
Security Level Provisioning or higher