Cisco ONS 15454 DWDM Installation and Operations Guide, R6.0
August 2005
Chapter 1 Install the Shelf and Common Control Cards
NTP-G1 Unpack and Inspect the Shelf Assembly
Test Equipment (ETSI)
To install the ONS 15454 ETSI, you need the following test equipment.
• Voltmeter
• Power meter (only for use with fiber optics)
• Bit error rate (BER) tester for E1-N-14, E1-42, E3-12, DS3i-N-12, STM1E-12, and FMEC cards
NTP-G1 Unpack and Inspect the Shelf Assembly
Step 1 Complete the “DLP-G1 Unpack and Verify the Shelf Assembly” task on page 1-6.
Step 2 Complete the “DLP-G2 Inspect the Shelf Assembly” task on page 1-7.
Step 3 Continue with the “NTP-G1 Unpack and Inspect the Shelf Assembly” procedure on page 1-6.
Stop. You have completed this procedure.
DLP-G1 Unpack and Verify the Shelf Assembly
Step 1 When you receive the ONS 15454 system equipment at the installation site, open the top of the box. The
Cisco Systems logo designates the top of the box.
Step 2 Remove the foam inserts from the box. The box contains the ONS 15454 shelf (wrapped in plastic) and
a smaller box of items needed for installation.
Step 3 To remove the shelf, grasp both rings of the shelf removal strap and slowly lift the shelf out of the box.
Step 4 Open the smaller box of installation materials, and verify that you have all items listed in the “Required
Tools and Equipment (ETSI)” section on page 1-4 or the “Required Tools and Equipment (ANSI)”
section on page 1-3.
Purpose This procedure explains how to unpack the ONS 15454 shelf assemblies
and verify their contents.
Tools/Equipment Pinned hex (Allen) key for front door
Prerequisite Procedures None
Required/As Needed Required
Onsite/Remote Onsite
Security Level None
Purpose This task removes the shelf assembly from the package.
Tools/Equipment None
Prerequisite Procedures None
Required/As Needed Required
Onsite/Remote Onsite
Security Level None