3-54
Cisco ONS 15454 DWDM Installation and Operations Guide, R6.0
September 2005
Chapter 3 Turn Up a Node
DLP-G66 Install Fiber-Optic Cables for a Hub Node
DLP-G66 Install Fiber-Optic Cables for a Hub Node
Note Throughout this task, west refers to Slots 1 through 8, and east refers to Slots 10 through 17.
Step 1 Refer to the Cisco MetroPlanner Internal Connections table (see Table 3-1 on page 3-3) for your site
when completing connections. Before you begin hub node connections, read the following rules:
• The west OPT-BST or OSC-CSM card common (COM) TX port is connected to the west
OPT-PRE COM RX port or the west 32DMX-O COM RX port.
• The west OPT-PRE COM TX port is connected to the west 32DMX-O COM RX port.
• The west 32MUX-O COM TX port is connected to the west OPT-BST or west OSC-CSM COM RX
port.
• The east 32MUX-O COM TX port is connected to the east OPT-BST or east OSC-CSM COM RX
port.
• The east OPT-BST or east OSC-CSM COM TX port is connected to the east OPT-PRE COM RX
port or the east 32DMX-O COM RX port.
• The east OPT-PRE COM TX port is connected to the east 32DMX-O COM RX port.
Figure 3-11 shows an example of a hub node with cabling. In the example, OSCM cards are installed. If
OSC-CSM are installed, they are usually installed in Slots 1 and 17.
Note Figure 3-11 is an example. Always install fiber-optic cables based on the Cisco MetroPlanner
Internal Connections table for your site.
Purpose This task installs fiber-optic cables on a hub node DWDM shelf.
Too ls Fiber-optic cables
Prerequisite Procedures NTP-G115 Clean Fiber Connectors, page 13-25
NTP-G139 Verify Cisco MetroPlanner Reports and Files, page 3-3
Required/As Needed As needed
Onsite/Remote Onsite
Security Level None