1-77
Cisco ONS 15454 DWDM Installation and Operations Guide, R6.0
August 2005
Chapter 1 Install the Shelf and Common Control Cards
DLP-G35 Inspect the Shelf Installation and Connections
Step 3 Complete the “DLP-G35 Inspect the Shelf Installation and Connections” task on page 1-77.
Step 4 Complete the “DLP-G36 Measure Voltage” task on page 1-78.
Step 5 Continue with Chapter 2, “Connect the PC and Log into the GUI.”
Stop. You have completed this procedure.
DLP-G35 Inspect the Shelf Installation and Connections
Step 1 Make sure all external wiring connections on the backplane (i.e. power, ground, alarms, etc.) are secure.
If a wire or cable is loose, return to the appropriate procedure in this chapter to correct it.
Step 2 (ETSI only) To check that the FMEC cover is seated correctly, verify that it can be easily closed without
disturbing cables.
Step 3 Return to your originating procedure (NTP).
NTP-G8 Install the Fan-Tray Assembly, page 1-40
NTP-G9 Install the Alarm Expansion Panel (ANSI Only), page 1-44
NTP-G10 Attach Wires to Alarm, Timing, LAN, and Craft Pin Connections, page
1-47
NTP-G11 Install an External Wire-Wrap Panel on the AEP (ANSI Only), page 1-58
NTP-G13 Install the Rear Cover (ANSI Only), page 1-64
NTP-G14 Install DWDM Equipment, page 1-66
NTP-G15 Install the Common Control Cards, page 1-71
Table 1-13 ONS 15454 ANSI Shelf Installation Task Summary (continued)
Description Completed
Purpose Use this task to inspect the shelf installation and connections and verify that
everything is installed and connected properly.
Tools/Equipment None
Prerequisite Procedures None
Required/As Needed Required
Onsite/Remote Onsite
Security Level None