Contents
vii
Cisco ONS 15454 DWDM Installation and Operations Guide, R6.0
August 2005
DLP- G273 Preprovision an SFP or XFP Slot 3-46
DLP- G64 Remove an SFP or XFP 3-47
NTP- G123 Install the Filler Cards 3-47
NTP- G34 Install Fiber-Optic Cables on DWDM Cards and DCUs 3-48
DLP- G65 Install Fiber-Optic Cables for OSC Link Terminations Between Two Adjacent Nodes 3-51
DLP- G66 Install Fiber-Optic Cables for a Hub Node 3-54
DLP- G67 Install Fiber-Optic Cables for a Terminal Node 3-56
DLP- G68 Install Fiber-Optic Cables for a Line Amplifier Node 3-58
DLP- G69 Install Fiber-Optic Cables for an OSC Regeneration Node 3-60
DLP- G70 Install Fiber-Optic Cables for an Amplified or Passive OADM Node 3-63
DLP- G71 Install Fiber-Optic Cables for an ROADM Node 3-68
NTP- G140 Install Fiber-Optic Cables Between a Terminal, Hub, or ROADM Node and the Transponder
Cards
3-72
DLP- G315 Install Fiber-Optic Cables From the 32WSS/32DMX and 32MUX-O/32DMX-O Cards to the
Patch Panel
3-74
DLP- G316 Install Fiber-Optic Cables from a TXP/MXP Node to the Patch Panel 3-78
NTP- G141 Install Fiber-Optic Cables for Y-Cable Protection Modules 3-79
NTP- G36 Calculate Cable Connections 3-80
DLP- G72 Create a DWDM Connection 3-81
DLP- G73 Delete a DWDM Connection 3-82
NTP- G138 Import a Cisco MetroPlanner Configuration File 3-82
NTP- G37 Run Automatic Node Setup 3-83
NTP- G38 Provision OSC Terminations 3-84
NTP- G39 Verify OSCM and OSC-CSM Transmit Power 3-86
DLP- G313 Verify OSC-CSM Transmit Power 3-87
DLP- G314 Verify OSCM Transmit Power 3-89
CHAPTER
4 Perform Node Acceptance Tests 4-1
Before You Begin 4-1
NTP- G41 Perform the Terminal or Hub Node with 32MUX-O and 32DMX-O Cards Acceptance Test 4-2
DLP- G268 Provision TXP_MR_2.5G Cards for Acceptance Testing 4-4
NTP- G42 Perform the Terminal Node with 32WSS and 32DMX Cards Acceptance Test 4-5
NTP- G43 Perform the ROADM Node Acceptance Test 4-8
DLP- G310 Verify ROADM Node Pass-Through Channels 4-12
DLP- G311 Verify the East ROADM Add/Drop Channels 4-16
DLP- G312 Verify the West ROADM Add/Drop Channels 4-18
NTP- G44 Perform the Anti-ASE Hub Node Acceptance Test 4-20
NTP- G45 Perform the Line Amplifier Node with OSCM Cards Acceptance Test 4-23