5-3
Cisco ONS 15454 Procedure Guide, R5.0
December 2004
Chapter 5 Turn Up Network
NTP-A124 Provision a Point-to-Point Network
• If the software is not the correct version, install the correct version from the ONS 15454 software
CD. Upgrade procedures are located in a release-specific software upgrade document.
TCC2/TCC2P cards can also be ordered with the latest software release.
• If the node defaults are not correct, import the network element defaults. Refer to the “Network
Element Defaults” appendix in the Cisco ONS 15454 Reference Manual.
Step 4 Click the Provisioning > General tabs. Verify that all general node information settings match the
settings of your site plan. If not, see the “NTP-A81 Change Node Management Information” procedure
on page 10-2.
Step 5 Click the Provisioning > Timing tabs. Verify that timing settings match the settings of your site plan.
If not, see the “NTP-A85 Change Node Timing” procedure on page 10-5.
Step 6 Click the Provisioning > Network tabs. Ensure that the IP settings and other CTC network access
information is correct. If not, see the “NTP-A201 Change CTC Network Access” procedure on
page 10-2.
Step 7 Click the Provisioning > Protection tabs. Verify that all protection groups have been created according
to your site plan. If not, see the “NTP-A203 Modify or Delete Card Protection Settings” procedure on
page 10-4.
Step 8 Click the Provisioning > Security tabs. Verify that all users have been created and their security levels
and policies match the settings indicated by your site plan. If not, see the “NTP-A205 Modify Users and
Change Security” procedure on page 10-6.
Step 9 If Simple Network Management Protocol (SNMP) is provisioned on the node, click the Provisioning >
SNMP tabs. Verify that all SNMP settings match the settings of your site plan. If not, see the “NTP-A87
Change SNMP Settings” procedure on page 10-6.
Step 10 Provision the network using the applicable procedure shown in the “Before You Begin” section on
page 5-1.
Stop. You have completed this procedure.
NTP-A124 Provision a Point-to-Point Network
Step 1 Complete the “DLP-A60 Log into CTC” task on page 17-66 on an ONS 15454 in the network where you
want to provision a point-to-point configuration. If you are already logged in, continue with Step 2.
Step 2 Click the Provisioning > Protection tabs. Verify that 1+1 protection is created for the OC-N cards.
Complete the “DLP-A73 Create a 1+1 Protection Group” task on page 17-81 if protection has not been
created.
Step 3 Repeat Steps 1 and 2 for the second point-to-point node.
Purpose This procedure provisions two ONS 15454s in a 1+1 point-to-point
(terminal) network.
Tools/Equipment None
Prerequisite Procedures NTP-A35 Verify Node Turn-Up, page 5-2
Required/As Needed As needed
Onsite/Remote Onsite
Security Level Provisioning and higher