11-2
Cisco ONS 15454 Procedure Guide, R5.0
December 2004
Chapter 11 Change Card Settings
NTP-A88 Modify Line Settings and PM Parameter Thresholds for Electrical Cards
NTP-A88 Modify Line Settings and PM Parameter Thresholds for
Electrical Cards
Step 1 Complete the “DLP-A60 Log into CTC” task on page 17-66 at the node where you want to change the
electrical card settings. If you are already logged in, proceed to Step 2.
Step 2 Complete the “NTP-A108 Back Up the Database” procedure on page 15-4 to preserve the existing
database.
Step 3 Perform any of the following tasks as needed:
• DLP-A165 Change Line and Threshold Settings for the DS1-14 or DS1N-14 Cards, page 18-28
• DLP-A166 Change Line and Threshold Settings for the DS3-12 or DS3N-12 Cards, page 18-32
• DLP-A167 Change Line and Threshold Settings for the DS3-12E or DS3N-12E Cards, page 18-36
• DLP-A168 Change Line and Threshold Settings for the DS3XM-6 Card, page 18-41
• DLP-A387 Change Line and Threshold Settings for the DS3XM-12 Card, page 20-74
• DLP-A526 Change Line and Threshold Settings for the DS3i-N-12 Cards, page 22-21
• DLP-A388 Change Line and Threshold Settings for the DS3/EC1-48 Cards, page 20-80
• DLP-A169 Change Line and Threshold Settings for the EC1-12 Card, page 18-45
Step 4 When you are finished changing the card settings, complete the “NTP-A108 Back Up the Database”
procedure on page 15-4.
Stop. You have completed this procedure.
NTP-A89 Modify Line Settings and PM Parameter Thresholds for
OC-N Cards
Purpose This procedure changes the line and threshold settings for electrical cards.
Tools/Equipment None
Prerequisite Procedures NTP-A17 Install the Electrical Cards, page 2-8
Required/As Needed As needed
Onsite/Remote Onsite or remote
Security Level Provisioning or higher
Purpose This procedure changes the line and threshold settings for optical cards.
Tools/Equipment None
Prerequisite Procedures NTP-A16 Install the OC-N Cards, page 2-6
Required/As Needed As needed
Onsite/Remote Onsite or remote
Security Level Provisioning or higher