1-8
Cisco ONS 15454 Procedure Guide, R5.0
March 2005
Chapter 1 Install the Shelf and Backplane Cable
NTP-A5 Install the EIAs
Caution Always use the supplied ESD wristband when working with a powered ONS 15454. Plug the wristband
cable into the ESD jack located on the lower-right outside edge of the shelf assembly.
Note EIAs are normally factory installed. Verify that the correct EIA is installed on the shelf assembly. If not,
install the correct EIA.
Note You do not need to power down the shelf before removing or installing an EIA. An in-service upgrade
of one EIA (A side or B side) is possible if all electrical traffic (DS-1, DS-3, DS3XM-6, and EC-1) is
being carried on the other side.
Step 1 Complete the “DLP-A12 Install a BNC or High-Density BNC EIA” task on page 17-12 as needed. BNCs
are locking connectors; the high-density BNC provides access to every port on every card.
Step 2 Complete the “DLP-A373 Install a MiniBNC EIA” task on page 20-57 as needed. The MiniBNC allows
up to 96 DS-3 circuits on each side of the ONS 15454.
Step 3 Complete the “DLP-A13 Install an SMB EIA” task on page 17-15 as needed. SMBs allow you to access
every port on every card using more space and efficient cabling.
Step 4 Complete the “DLP-A14 Install the AMP Champ EIA” task on page 17-16 as needed. AMP Champs are
exclusive to DS-1 cables.
Step 5 Complete the “DLP-A190 Install a UBIC-V EIA” task on page 18-61 as needed. The UBIC-V (vertical)
EIAs allow you to use high-density electrical cards. The UBIC-V EIAs provide SCSI connectors.
Step 6 Complete the “DLP-A399 Install a UBIC-H EIA” task on page 20-97 as needed. The UBIC-H
(horizontal) EIAs allow you to use high-density electrical cards. The UBIC-H EIAs provide SCSI
connectors.
Note To attach cables to the EIAs, see the “NTP-A9 Install the Electrical Card Cables on the
Backplane” procedure on page 1-21.
Step 7 Continue with the “NTP-A6 Install the Power and Ground” procedure on page 1-9.
Stop. You have completed this procedure.
Onsite/Remote Onsite
Security Level None

Table of Contents

Other manuals for Cisco ONS 15454 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Cisco ONS 15454 Series and is the answer not in the manual?

Cisco ONS 15454 Series Specifications

General IconGeneral
Supported InterfacesEthernet
ManagementCisco Transport Controller (CTC), TL1, SNMP
Power Supply-48 VDC or AC (depending on power supply module)
Operating Temperature0 to 50°C (32 to 122°F) - varies by module
Storage Temperature-40°C to 70°C (-40 to 158°F)
Relative Humidity5 to 95%, noncondensing
Supported ProtocolsSONET/SDH, Ethernet, OTN
Platform TypeMulti-service transport platform