2.35.6 Scheme and activation
VCHK1 and VCHK2 provide output signals to the ARC with results of voltage check and
synchronism check as described earlier. The energizing control scheme of VCHK1 is drawn in
Figure 2.35-10, the output signal ARC1-VCHK is fed to ARC1 when one or more of the
following conditions are established: (1) the VCHK1 runs, (2) the OVB and the UVL run, or (3)
the UVB and the OVL run. The activation of VCHK1 is controlled by using the scheme
switches: [ARC1-LB_DL], [ARC1-DB_LL], [ARC1-DB_DL], and [ARC1-SYN1]. For example,
DB_LL in Table 2.35-2 is only the criteria for ARC1 operation, On is set for the scheme switch
[ARC1-DB_LL] while Off is set for other scheme switches. As a result, the system is energized
in the direction from line to bus with ARC1. As shown in Figure 2.35-11, the operation of the
VCHK2 is also applicable in accordance with Figure 2.35-3 similar to VCHK1. Note that the
SYN1-df and SYN2-df operations are nullified when Off are set for the [SYN1-dfEN] and
[SYN2-dfEN].
L3
OVL
OVB
8200011B62
≥1
ARC1-LB_DL
OVB
&
&
&
UVB
OVL
L1
L2
8000011B63
8300011B60
OVL
8C00011B67
8D00011B68
8E00011B69
UVL
8100011B61
UVL
T_OVL3P
t 0
0.01-100.00S
VCHK_OVL3P
&
&
T_LB_DL
t 0
0.01-100.00S
T_DB_LL
t 0
0.01-100.00S
T_DB_DL
t 0
0.01-100.00S
ARC1-DB_LL
ON
ON
&
8000011B6D
8100011B6E
8F00011B6F
ARC1-DB_DL
ON
&
8200011B70
8000011B23
OVB
OVL
&
SYN1-
SYN1-dV
SYN1-df
T_SYN1
t 0
0.01-100.00S
ARC1-SYN1
ON
&
8300011B72
ARC1-NOVCHK
ON
8400011B64
8500011B65
8600011B66
8300011B71
SYN1-dfEN
OFF
≥1
ARC1-VCHK
Figure 2.35-10 Logic of VCHK1