EasyManua.ls Logo

Toshiba GR200 Series - (viii)-2 Output signal to BO; (ix) Receiving “operate command P3-control” using the PLC function; (ix)-1 Input signal required to connect

Toshiba GR200 Series
1770 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
6F2S1914 (0.49)
GRL200 (Soft 033 & 037)
- 950 -
LGP1EXOT]. If the signal is to be issued from the logic programmed by the user
instead of the logic shown in Figure 4.9-26, connect the “operate completed” signal
generated in the user-programmed logic to connection point#2 “User configurable
condition”. That is, set the scheme switch [TPOS01-LGP1EXOT] to PLC and use
TPOS01IN_TMP_38”.
††
Note: To identify the input and output signals of the other TPOS logics, see Table
4.9-16 for PLC#2, Table 4.9-17 for PLC#3 and Table 4.9-20 for the outputs.
Output signal to BO
The TPOS01 function, in Figure 4.9-41, can issue a signal Operate P2-controlat output point
TPOS01_P2EX_BO”, when the TPOS01 function determines that the “PLC-P2-Control” signal
is true.
(ix) Receiving “operate command P3-control” using the PLC function
Figure 4.9-42 outlines the reception of the operate command P3-control by the PLC function.
Signal generation by
the PLC function
P2 control by the PLC function
Do nothing
Operation
decision
Success
Failed
Operate logic
P1 control from the remote-end
P2 control from the remote-end
P3 control from the remote end
P1 control from the local-end
P3 control from the local-end
P2 control from the local-end
P1 control by the PLC function
Wait for a command
P2 control by the PLC function
P3 control by the PLC function
Select logics
Signal output
P3 control from the remote end
P1 control from the local-end
P1 control from the remote-end
P2 control from the remote-end
P2 control from the local-end
P3 control from the local-end
P1 control by the PLC function
P3 control by the PLC function
Wait for a next command
Figure 4.9-42 Outline of operate command P3-control’
Input signal required to connect
Figure 4.9-43 depicts the operate logic when an Operate command P3 (PLC-P3-Control)”
signal is generated by the PLC function. There are two input points for reception of this
command signal, like the signal Operate command P1 (PLC-P1-Control)”. That is, if an
interlock check is required, apply the signal at connection point (PLC#3:i.e.,
DEV01_P3_INTERLOCK). If, on the other hand, an interlock check is not required, apply the
signal at connection point (PLC#4:i.e., DEV01_P3_COMMAND). We shall assume the PLC#3
and PLC#4 as PLC#1 and PLC#2 in Table 4.9-4. Note that the user should set PLC for scheme

Table of Contents