Power analysis (option R&S RTE-K31)
R&S
®
RTE
997User Manual 1326.1032.02 ─ 20
The used resources are listed in the "Details" tab. See also: Chapter 16.2.3, "Details
tab", on page 966.
The" Turn on time" is measured as the time between the trigger point ("Trigger level
on" value is reached) and the time the given percentage of the "Steady state level" is
reached.
The" Turn off time" is measured as the time between the trigger point, delayed with the
set "Time" ("Trigger level on" value is reached) and the time the given percentage of
the "Steady state level" is reached, see
See also Figure 16-2 and Figure 16-3
The following remote commands are used for handling the measurement results:
●
POWer:ONOFf:RESult:TOFF? on page 1967
●
POWer:ONOFf:RESult:TON? on page 1967
●
POWer:ONOFf:REPort:ADD on page 1966
16.5.2.2 Configuring turn on/ off
For details of the configuration settings, see Chapter 16.5.2.3, "Turn on/off settings",
on page 998.
1. Select "Analysis">"Power".
2. Under "Power Path", select "Turn on/off ".
3. Connect the probes to the DUT as shown in the "Channels" tab:
Power path