January 2007
2-803
WorkCentre 7132
123-203, 123-207
Status-indicator-raps
Revision
123-203 UI Controller RAP
The send request queue is full.
Initial Actions
Power Off/On
Procedure
Disconnect and reconnect the electrical connections on the UI PWB (PL 13.2) and P/J388 on
the ESS PWB (PL 11.2)
If the problem persists reload Software (ADJ 9.3.1).
If the problem persists replace the UI PWB (PL 13.2).
If the problem persists replace the ESS PWB (PL 11.2)
123-207 Communication Manager Target RAP
A mailbox operations value is incorrect.
Initial Actions
Power Off/On
Procedure
Disconnect and reconnect the electrical connections on the UI PWB (PL 13.2) and P/J388 on
the ESS PWB (PL 11.2)
If the problem persists reload Software (ADJ 9.3.1).
If the problem persists replace the UI PWB (PL 13.2).
If the problem persists replace the ESS PWB (PL 11.2)

Table of Contents

Other manuals for Xerox WorkCentre 7132

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Xerox WorkCentre 7132 and is the answer not in the manual?

Xerox WorkCentre 7132 Specifications

General IconGeneral
BrandXerox
ModelWorkCentre 7132
CategoryAll in One Printer
LanguageEnglish

Related product manuals